Construction works are progressing well!
✅ Waldegrave Road & Burghley Road: Nearing completion! Threshold slabs, a new tree, and planting are scheduled for installation by the end of May.
? Vernon Road Junction: Works began this week and are expected to wrap up by the end of June.
Thank you for your patience as we enhance the area for everyone! ?‍♀️?